The Java development of a project is outsourced to India. The project schedule is starting to slip.
What is the LEAST likely cause of the slippage?
A. Lack of competent programmers
B. Cultural influences
C. Internationalization
D. Communication
Answer: A
Explanation:


PM 沒料D p仔先唔做野

本帖最後由 takayo72 於 2016-6-30 17:29 編輯

條問題咁general, A,B,C,D 都可以係原因,問題在實際乜嘢context


呢啲真係搞好彩撞啱

TOP

回覆 2# takayo72


    1 個 braindump 3千幾題, 1100 頁

TOP

條問題咁general, A,B,C,D 都可以係原因,問題在實際乜嘢context


呢啲真係搞好彩撞啱 ...
takayo72 發表於 2016-6-30 17:27



    係唔係因為p仔係當resource,起原本schedule個度已經預計埋,所以唔會推遲?

TOP

LEAST likely = 最沒可能.

個ans. make sense 喎. 有乜問題?

TOP

回覆 1# idler


    E. Lack of resource ^^

TOP

係唔係因為p仔係當resource,起原本schedule個度已經預計埋,所以唔會推遲? ...
044003 發表於 2016-6-30 23:19



    係 competency 係 measurable
但係其他三樣野 not measurable, 做左先知, 即係 uncertainty 好高

TOP

LEAST likely = 最沒可能.

個ans. make sense 喎. 有乜問題?
sozu 發表於 2016-7-1 00:38

可能因為佢覺得太簡單

TOP

有無師兄都條讀緊PMP?

TOP

回覆  idler


    E. Lack of resource ^^
l0001 發表於 2016-7-1 04:00


Lack of budget
Lack of money to hire competent programmers